Quick answer
The plants came online in 2019.[1] Two of the two plants with a recorded mounting type use tracking systems that follow the sun, and no use fixed-tilt panels.[1]
| Plant | Online | Capacity (MW AC) | Mounting |
|---|---|---|---|
| Meridian III | 2019 | 52.5 | Tracking |
| Meridian II | 2019 | 5 | Tracking |
Source: U.S. Large-Scale Solar Photovoltaic Database (USGS, LBNL), version 4.0, released April 14, 2026. Data compiled November 1, 2026.
The oldest utility-scale solar plant in the county came online in 2019.[1] Solar lease agreements can last 20 to 30 years.[2] Federal guidance for farmers describes solar lease payments as typically structured as a fixed annual or monthly fee per acre, or as a percentage of the energy generated by the solar panels.[3] Rent during the operations period will likely include an inflation adjustment, which may be tied to a measure like the Consumer Price Index or set at a fixed rate.[4]
What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest. Solar rent is paid period by period, the operations period may last 20 years or more, and renewals are at the developer's option.[4] The land can be converted back to agricultural uses at the end of the installation's operational life.[3]
Educational information only — not legal, tax, or investment advice. The figures are public reference data, not a valuation or appraisal of any interest. Consult a qualified attorney, CPA, or landman about your specific situation.
Lauderdale County, Mississippi has two utility-scale solar plants of at least 1 MW, with 57.5 MW (AC) of capacity in total, according to the U.S. Large-Scale Solar Photovoltaic Database (version 4.0, released April 14, 2026).[1] Utility-scale power plants have at least one megawatt of electricity generation capacity.[5]
The plants are Meridian III (2019, 52.5 MW AC) and Meridian II (2019, 5 MW AC).[1]
Buckhead Energy buys solar lease payments and solar royalties. What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest.
Of the plants with a recorded year, two came online in the 2010s.[1] Solar lease agreements can last 20 to 30 years.[2]
Nearby Mississippi counties with utility-scale solar plants include Clarke County (78.5 MW AC), Lowndes County (400 MW AC), Scott County (175 MW AC), Madison County (100 MW AC) and Lamar County (104 MW AC).[1]
Solar Lease Payments and Royalties in Mississippi
Selling Solar Lease Payments and Solar Royalties
Oil and gas mineral rights in Lauderdale County, Mississippi
Solar Lease Payments and Royalties in Clarke County
Solar Lease Payments and Royalties in Lowndes County
Solar Lease Payments and Royalties in Scott County
[1] U.S. Large-Scale Solar Photovoltaic Database (version 4.0, released April 14, 2026) — U.S. Geological Survey and Lawrence Berkeley National Laboratory (accessed November 1, 2026)
[2] Solar Lease Considerations for Landowners — Texas A&M AgriLife Extension (accessed November 1, 2026)
[3] Farmer's Guide to Going Solar — U.S. Department of Energy (accessed November 1, 2026)
[4] Farmland Owner's Guide to Solar Leasing — Ohio State University Extension and the National Agricultural Law Center (accessed November 1, 2026)
[5] Solar explained: Where solar is found and used — U.S. Energy Information Administration (accessed November 1, 2026)
Buckhead Energy buys solar lease payments and solar royalties.