The projects came online between 2010 and 2026.[1] Four of these projects also have turbines outside Kit Carson County; the table counts only the turbines in the county.[1] Turbine makers represented in the county: GE Wind (301 turbines) and Vestas (127 turbines).[1]
325 of the 753 turbines in the county have no recorded capacity in the database, so the megawatt figures count the rest.[1]
| Project | Online | Turbines in the county | Capacity in the county (MW) |
|---|---|---|---|
| Bronco Plains | 2020 | 108 | 299.4 |
| Bronco Plains Wind II | 2023 | 72 | 199 |
| Cheyenne Ridge | 2020 | 76 | 165.6 |
| Carousel | 2015 | 87 | 147.9 |
| Crossing Trails | 2021 | 20 | 86 |
| Rush Creek II | 2018 | 30 | 60 |
| Kit Carson Project | 2010 | 34 | 51 |
| Rush Creek I | 2018 | 1 | 2 |
| Unnamed project (Kit Carson County) | 2026 | 325 | Not recorded |
Source: U.S. Wind Turbine Database (USGS, ACP, LBNL), version 9.1, released September 28, 2026. Data compiled November 3, 2026.
Turbines at the oldest project in the county have been in place since 2010.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2] The newest project here came online in 2026.[1] In royalty arrangements, the developer pays the landowner a percentage of the revenue received from the electricity produced by the turbines.[2] Minimum payments serve as a floor so landowners receive some revenue even when maintenance outages or lower winds cut production in a given year.[2]
What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest. A wind lease rents land for a term of years, and wind power leases generally have terms of 20 to 40 years, often with an option for extending the lease.[2] Under a wind lease, the landowner typically keeps the right to continue to grow crops, raise cattle or otherwise use the land outside the project.[2]
Educational information only — not legal, tax, or investment advice. The figures are public reference data, not a valuation or appraisal of any interest. Consult a qualified attorney, CPA, or landman about your specific situation.
Kit Carson County, Colorado has nine operating wind projects with 753 turbines and 1,010.9 MW of recorded capacity in the county, according to the U.S. Wind Turbine Database (version 9.1, released September 28, 2026).[1] 325 of the 753 turbines in the county have no recorded capacity in the database, so the megawatt figures count the rest.[1]
The projects are Bronco Plains (2020, 299.4 MW), Bronco Plains Wind II (2023, 199 MW), Cheyenne Ridge (2020, 165.6 MW), Carousel (2015, 147.9 MW), Crossing Trails (2021, 86 MW), Rush Creek II (2018, 60 MW), Kit Carson Project (2010, 51 MW) and Rush Creek I (2018, 2 MW), plus one more in the table above.[1]
Buckhead Energy buys wind lease payments and wind royalties. What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest.
Of the projects with a recorded year, four came online in the 2010s and five in the 2020s.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2]
Nearby Colorado counties with wind projects include Cheyenne County (370.8 MW), Lincoln County (893.8 MW), Elbert County (473 MW), El Paso County (246.5 MW) and Prowers County (241.8 MW).[1]
Wind Royalties and Lease Payments in Colorado
Selling Wind Royalties and Wind Lease Payments
Oil and gas mineral rights in Kit Carson County, Colorado
Wind Royalties and Lease Payments in Cheyenne County
Wind Royalties and Lease Payments in Lincoln County
Wind Royalties and Lease Payments in Elbert County
[1] U.S. Wind Turbine Database (version 9.1, released September 28, 2026) — U.S. Geological Survey, American Clean Power Association and Lawrence Berkeley National Laboratory (accessed November 1, 2026)
[2] New York Wind Energy Guide for Local Decision Makers: Land Agreements — New York State Energy Research and Development Authority (NYSERDA) (accessed November 1, 2026)
Buckhead Energy buys wind lease payments and wind royalties.
Get a Free Written Offer