Quick answer
The projects came online between 2011 and 2018.[1] Four of these projects also have turbines outside Lincoln County; the table counts only the turbines in the county.[1] Turbine makers represented in the county: GE Wind (347 turbines) and Vestas (174 turbines).[1]
| Project | Online | Turbines in the county | Capacity in the county (MW) |
|---|---|---|---|
| Limon III | 2014 | 118 | 200.6 |
| Limon II | 2012 | 125 | 200 |
| Cedar Point | 2011 | 106 | 190.8 |
| Limon I | 2012 | 104 | 166.4 |
| Rush Creek II | 2018 | 59 | 118 |
| Rush Creek I | 2018 | 9 | 18 |
Source: U.S. Wind Turbine Database (USGS, ACP, LBNL), version 9.1, released September 28, 2026. Data compiled November 3, 2026.
Turbines at the oldest project in the county have been in place since 2011.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2] The newest project here came online in 2018.[1] In royalty arrangements, the developer pays the landowner a percentage of the revenue received from the electricity produced by the turbines.[2] Minimum payments serve as a floor so landowners receive some revenue even when maintenance outages or lower winds cut production in a given year.[2]
What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest. A wind lease rents land for a term of years, and wind power leases generally have terms of 20 to 40 years, often with an option for extending the lease.[2] Under a wind lease, the landowner typically keeps the right to continue to grow crops, raise cattle or otherwise use the land outside the project.[2]
Educational information only — not legal, tax, or investment advice. The figures are public reference data, not a valuation or appraisal of any interest. Consult a qualified attorney, CPA, or landman about your specific situation.
Lincoln County, Colorado has six operating wind projects with 521 turbines and 893.8 MW of recorded capacity in the county, according to the U.S. Wind Turbine Database (version 9.1, released September 28, 2026).[1]
The projects are Limon III (2014, 200.6 MW), Limon II (2012, 200 MW), Cedar Point (2011, 190.8 MW), Limon I (2012, 166.4 MW), Rush Creek II (2018, 118 MW) and Rush Creek I (2018, 18 MW).[1]
Buckhead Energy buys wind lease payments and wind royalties. What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest.
Of the projects with a recorded year, six came online in the 2010s.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2]
Nearby Colorado counties with wind projects include Elbert County (473 MW), El Paso County (246.5 MW), Kit Carson County (1,010.9 MW), Cheyenne County (370.8 MW) and Jefferson County (7.1 MW).[1]
Wind Royalties and Lease Payments in Colorado
Selling Wind Royalties and Wind Lease Payments
Oil and gas mineral rights in Lincoln County, Colorado
Wind Royalties and Lease Payments in Elbert County
Wind Royalties and Lease Payments in El Paso County
Wind Royalties and Lease Payments in Kit Carson County
[1] U.S. Wind Turbine Database (version 9.1, released September 28, 2026) — U.S. Geological Survey, American Clean Power Association and Lawrence Berkeley National Laboratory (accessed November 1, 2026)
[2] New York Wind Energy Guide for Local Decision Makers: Land Agreements — New York State Energy Research and Development Authority (NYSERDA) (accessed November 1, 2026)
Buckhead Energy buys wind lease payments and wind royalties.
Get a Free Written Offer