Quick answer
The projects came online between 2003 and 2023.[1] Five of these projects also have turbines outside Murray County; the table counts only the turbines in the county.[1] Turbine makers represented in the county: GE Wind (199 turbines), Suzlon (11 turbines) and Siemens (6 turbines).[1]
| Project | Online | Turbines in the county | Capacity in the county (MW) |
|---|---|---|---|
| Fenton | 2007 | 117 | 175.5 |
| Northern Wind Repower | 2023 | 37 | 100 |
| Moraine Wind Power project | 2003 | 26 | 39 |
| Rock Aetna | 2022 | 8 | 21.8 |
| Moraine II | 2009 | 13 | 19.5 |
| Ridgewind | 2010 | 6 | 13.8 |
| East Ridge | 2006 | 8 | 10 |
| Valley View | 2011 | 5 | 10 |
| Stoneray | 2018 | 3 | 7.9 |
| Minnesota Wind Share | 2006 | 3 | 5.4 |
Source: U.S. Wind Turbine Database (USGS, ACP, LBNL), version 9.1, released September 28, 2026. Data compiled November 3, 2026.
Turbines at the oldest project in the county have been in place since 2003.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2] The newest project here came online in 2023.[1] In royalty arrangements, the developer pays the landowner a percentage of the revenue received from the electricity produced by the turbines.[2] Minimum payments serve as a floor so landowners receive some revenue even when maintenance outages or lower winds cut production in a given year.[2]
What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest. A wind lease rents land for a term of years, and wind power leases generally have terms of 20 to 40 years, often with an option for extending the lease.[2] Under a wind lease, the landowner typically keeps the right to continue to grow crops, raise cattle or otherwise use the land outside the project.[2]
Educational information only — not legal, tax, or investment advice. The figures are public reference data, not a valuation or appraisal of any interest. Consult a qualified attorney, CPA, or landman about your specific situation.
Murray County, Minnesota has 10 operating wind projects with 226 turbines and 402.9 MW of recorded capacity in the county, according to the U.S. Wind Turbine Database (version 9.1, released September 28, 2026).[1]
The projects are Fenton (2007, 175.5 MW), Northern Wind Repower (2023, 100 MW), Moraine Wind Power project (2003, 39 MW), Rock Aetna (2022, 21.8 MW), Moraine II (2009, 19.5 MW), Ridgewind (2010, 13.8 MW), East Ridge (2006, 10 MW) and Valley View (2011, 10 MW), plus two more in the table above.[1]
Buckhead Energy buys wind lease payments and wind royalties. What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest.
Of the projects with a recorded year, five came online in the 2000s, three in the 2010s and two in the 2020s.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2]
Nearby Minnesota counties with wind projects include Pipestone County (302.1 MW), Nobles County (539.3 MW), Rock County (319.4 MW), Lyon County (18.9 MW) and Lincoln County (1,018.9 MW).[1]
Wind Royalties and Lease Payments in Minnesota
Selling Wind Royalties and Wind Lease Payments
Wind Royalties and Lease Payments in Pipestone County
Wind Royalties and Lease Payments in Nobles County
Wind Royalties and Lease Payments in Rock County
[1] U.S. Wind Turbine Database (version 9.1, released September 28, 2026) — U.S. Geological Survey, American Clean Power Association and Lawrence Berkeley National Laboratory (accessed November 1, 2026)
[2] New York Wind Energy Guide for Local Decision Makers: Land Agreements — New York State Energy Research and Development Authority (NYSERDA) (accessed November 1, 2026)
Buckhead Energy buys wind lease payments and wind royalties.
Get a Free Written Offer