(817) 778-9532

Wind Royalties and Lease Payments in Nobles County, Minnesota

Quick answer

Buckhead Energy buys wind lease payments and wind royalties. Nobles County, Minnesota has nine operating wind projects with 255 turbines and 539.3 MW of recorded capacity in the county, according to the U.S. Wind Turbine Database (version 9.1, released September 28, 2026).

Wind projects in Nobles County

The projects came online between 2001 and 2023.[1] One of these projects also has turbines outside Nobles County; the table counts only the turbines in the county.[1] Turbine makers represented in the county: GE Wind (153 turbines), Vestas (89 turbines) and NEG Micon (7 turbines).[1]

One of the 255 turbines in the county has no recorded capacity in the database, so the megawatt figures count the rest.[1]

ProjectOnlineTurbines in the countyCapacity in the county (MW)
Nobles 2 Power Partners202074250.4
Nobles2010133213.1
Community Wind South20121430.8
Fenton20072030
Wolf200656.3
Missouri River Energy Services (MRES)200365.5
Arnold Wind Farm200511.7
Wilmont Hills200111.5
Unnamed project (Nobles County)20231Not recorded

Source: U.S. Wind Turbine Database (USGS, ACP, LBNL), version 9.1, released September 28, 2026. Data compiled November 3, 2026.

What the data means for wind lease owners in Nobles County

Turbines at the oldest project in the county have been in place since 2001.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2] The newest project here came online in 2023.[1] In royalty arrangements, the developer pays the landowner a percentage of the revenue received from the electricity produced by the turbines.[2] Minimum payments serve as a floor so landowners receive some revenue even when maintenance outages or lower winds cut production in a given year.[2]

What you sell and what you keep

What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest. A wind lease rents land for a term of years, and wind power leases generally have terms of 20 to 40 years, often with an option for extending the lease.[2] Under a wind lease, the landowner typically keeps the right to continue to grow crops, raise cattle or otherwise use the land outside the project.[2]

Educational information only — not legal, tax, or investment advice. The figures are public reference data, not a valuation or appraisal of any interest. Consult a qualified attorney, CPA, or landman about your specific situation.

Frequently asked questions

How many wind projects are in Nobles County, Minnesota?

Nobles County, Minnesota has nine operating wind projects with 255 turbines and 539.3 MW of recorded capacity in the county, according to the U.S. Wind Turbine Database (version 9.1, released September 28, 2026).[1] One of the 255 turbines in the county has no recorded capacity in the database, so the megawatt figures count the rest.[1]

Which wind projects operate in Nobles County?

The projects are Nobles 2 Power Partners (2020, 250.4 MW), Nobles (2010, 213.1 MW), Community Wind South (2012, 30.8 MW), Fenton (2007, 30 MW), Wolf (2006, 6.3 MW), Missouri River Energy Services (MRES) (2003, 5.5 MW), Arnold Wind Farm (2005, 1.7 MW) and Wilmont Hills (2001, 1.5 MW), plus one more in the table above.[1]

Can I sell wind lease payments or royalties in Nobles County?

Buckhead Energy buys wind lease payments and wind royalties. What Buckhead buys depends on the deal, and Buckhead tells the seller up front which interest it is offering to buy — for example, the payments for the rest of the current lease term, a term easement, or a longer-term interest.

When did wind projects in Nobles County come online?

Of the projects with a recorded year, five came online in the 2000s, two in the 2010s and two in the 2020s.[1] Wind power leases generally have terms of 20 to 40 years, often with an option to extend, while a typical utility-scale wind power project has a useful life of 20 years.[2]

Which nearby Minnesota counties also have wind projects?

Nearby Minnesota counties with wind projects include Murray County (402.9 MW), Rock County (319.4 MW), Pipestone County (302.1 MW), Jackson County (601.8 MW) and Lyon County (18.9 MW).[1]

Related pages

Wind Royalties and Lease Payments in Minnesota

Selling Wind Royalties and Wind Lease Payments

Wind Royalties and Lease Payments in Murray County

Wind Royalties and Lease Payments in Rock County

Wind Royalties and Lease Payments in Pipestone County

Wind Royalties and Lease Payments in Jackson County

Wind Royalties and Lease Payments in Lyon County

Sources

[1] U.S. Wind Turbine Database (version 9.1, released September 28, 2026) — U.S. Geological Survey, American Clean Power Association and Lawrence Berkeley National Laboratory (accessed November 1, 2026)

[2] New York Wind Energy Guide for Local Decision Makers: Land Agreements — New York State Energy Research and Development Authority (NYSERDA) (accessed November 1, 2026)

Ready to Sell Your Wind Lease Payments or Royalties?

Buckhead Energy buys wind lease payments and wind royalties.

Get a Free Written Offer